๐—ก๐—ฒ๐˜„ ๐—ฆ๐—ผ๐—ฐ๐—ถ๐—ฒ๐˜๐˜† ๐—ก๐—›๐—ฆ: ๐—๐—ผ๐—ถ๐—ป๐˜ ๐—•๐˜‚๐—ถ๐—น๐—ฑ๐—ถ๐—ป๐—ด ๐—œ๐—ป๐˜€๐—ฝ๐—ฒ๐—ฐ๐˜๐—ถ๐—ผ๐—ป ๐—จ๐—ฝ๐—ฑ๐—ฎ๐˜๐—ฒ

Representatives from the Schools Division Office โ€” General Santos City and engineers from the City Engineering Office conducted a joint building inspection at New Society National High School on June 9-10, 2026, following the magnitude 7.8 earthquake on June 8.

The inspection team of structural engineers and safety officers assessed the buildingsโ€™ structural integrity, documented visible damage, and recommended immediate and long-term measures to ensure the safety of students and staff.

Principal III Maโ€™am Hanena L. Epino thanked the Schools Division and City Engineering Office for their prompt technical assistance and reaffirmed the schoolโ€™s commitment to protecting its learners and personnel.